- Commissioning Plan / 10 days / 24-Dec-08 / 16-Jan-09 / Ibnu
- Power source (Off/On-Plot) / 5 days / 17-Jan-09 / 21-Jan-09 / T.B.A
- Substation / 5 days / 22-Jan-09 / 26-Jan-09 / T.B.A
- Cable tray (visual check list only) / 2 days / 27-Jan-09 / 28-Jan-09 / T.B.A
- Lighting / 2 days / 29-Jan-09 / 30-Jan-09 / T.B.A
- Roads & drainage system / 3 days / 17-Jan-09 / 19-Jan-09 / Sabik
- Major pipe racks / 2 days / 17-Jan-09 / 18-Jan-09 / Sabik
- Kill water / 3 days / 19-Jan-09 / 21-Jan-09 / Frenky
- Air compressor package performance test / 5 days / 22-Jan-09 / 26-Jan-09 / Agung
- Overflow Tanks (Refurbishment), Overflow Pumps & Priming Chamber / 5 days / 27-Jan-09 / 31-Jan-09 / Saepudin
- Storm water pump / 2 days / 1-Feb-09 / 2-Feb-09 / Saepudin
- Manifold (loop and function test for on/off valve) / 5 days / 3-Feb-09 / 7-Feb-09 / Wawan
- KO Drum (Visual check list and Loop test procedure for E/I) / 2 days / 8-Feb-09 / 9-Feb-09 / Saepudin
- Vent stack (Visual check list and Loop test procedure for E/I) / 2 days / 10-Feb-09 / 11-Feb-09 / Saepudin
- Utility Chemical Injection / 5 days / 12-Feb-09 / 16-Feb-09 / Saepudin
- AWT Pump A/B/C/D + AWT Separator A/B/C/D / 5 days / 17-Feb-09 / 21-Feb-09 / Yozi
- Condensate Separator + Condensate Transfer Pump / 5 days / 22-Feb-09 / 26-Feb-09 / Yozi
- Utility Fuel gas (procedure for piping visual check only) / 5 days / 27-Feb-09 / 3-Mar-09 / Riyanto
- Surge vessel + Production Transfer Pump / 5 days / 4-Mar-09 / 8-Mar-09 / Yozi
- GLCC (Refurbishment) (Visual check list and Loop test procedure for E/I) / 5 days / 9-Mar-09 / 13-Mar-09 / Saepudin
- Utility Steam (procedure of visual check for piping only) / 5 days / 14-Mar-09 / 18-Mar-09 / Riyanto
- Enclosed Flare (Refurbishment) / 5 days / 19-Mar-09 / 23-Mar-09 / Yozi
- Condensate Air Cooler (Refurbishment) / 5 days / 24-Mar-09 / 28-Mar-09 / Saepudin
- Control and Monitoring (SCADA) (see detail at schedule below) / 15 days / 17-Jan-09 / 31-Jan-09 / Wawan
- Telecomunication / 15 days / 17-Jan-09 / 31-Jan-09 / Wawan
- Feed Heater A/B (visual check only) / 2 days / 1-Feb-09 / 2-Feb-09 / Saepudin
- CVC Separator + CVC Pump / 5 days / 3-Feb-09 / 7-Feb-09 / Yozi
- CVC Condensate Separator + CVC Condensate pump / 5 days / 8-Feb-09 / 12-Feb-09 / Yozi
- CVC Air Cooler / 5 days / 13-Feb-09 / 17-Feb-09 / Saepudin
- SOP for start-up / 30 days / 10-Feb-09 / 11-Mar-09 / Coord : Saepudin
Jumat, 16 Januari 2009
COMMISSIONING PROCEDURE DEVELOPMENT SCHEDULE
Legend (How to read) : Commissioning Document / Duration / Start date / Finished Date / PIC