COMMISSIONING PROCEDURE DEVELOPMENT SCHEDULE

Legend (How to read) : Commissioning Document / Duration / Start date / Finished Date / PIC

  1. Commissioning Plan / 10 days / 24-Dec-08 / 16-Jan-09 / Ibnu
  2. Power source (Off/On-Plot) / 5 days / 17-Jan-09 / 21-Jan-09 / T.B.A
  3. Substation / 5 days / 22-Jan-09 / 26-Jan-09 / T.B.A
  4. Cable tray (visual check list only) / 2 days / 27-Jan-09 / 28-Jan-09 / T.B.A
  5. Lighting / 2 days / 29-Jan-09 / 30-Jan-09 / T.B.A
  6. Roads & drainage system / 3 days / 17-Jan-09 / 19-Jan-09 / Sabik
  7. Major pipe racks / 2 days / 17-Jan-09 / 18-Jan-09 / Sabik
  8. Kill water / 3 days / 19-Jan-09 / 21-Jan-09 / Frenky
  9. Air compressor package performance test / 5 days / 22-Jan-09 / 26-Jan-09 / Agung
  10. Overflow Tanks (Refurbishment), Overflow Pumps & Priming Chamber / 5 days / 27-Jan-09 / 31-Jan-09 / Saepudin
  11. Storm water pump / 2 days / 1-Feb-09 / 2-Feb-09 / Saepudin
  12. Manifold (loop and function test for on/off valve) / 5 days / 3-Feb-09 / 7-Feb-09 / Wawan
  13. KO Drum (Visual check list and Loop test procedure for E/I) / 2 days / 8-Feb-09 / 9-Feb-09 / Saepudin
  14. Vent stack (Visual check list and Loop test procedure for E/I) / 2 days / 10-Feb-09 / 11-Feb-09 / Saepudin
  15. Utility Chemical Injection / 5 days / 12-Feb-09 / 16-Feb-09 / Saepudin
  16. AWT Pump A/B/C/D + AWT Separator A/B/C/D / 5 days / 17-Feb-09 / 21-Feb-09 / Yozi
  17. Condensate Separator + Condensate Transfer Pump / 5 days / 22-Feb-09 / 26-Feb-09 / Yozi
  18. Utility Fuel gas (procedure for piping visual check only) / 5 days / 27-Feb-09 / 3-Mar-09 / Riyanto
  19. Surge vessel + Production Transfer Pump / 5 days / 4-Mar-09 / 8-Mar-09 / Yozi
  20. GLCC (Refurbishment) (Visual check list and Loop test procedure for E/I) / 5 days / 9-Mar-09 / 13-Mar-09 / Saepudin
  21. Utility Steam (procedure of visual check for piping only) / 5 days / 14-Mar-09 / 18-Mar-09 / Riyanto
  22. Enclosed Flare (Refurbishment) / 5 days / 19-Mar-09 / 23-Mar-09 / Yozi
  23. Condensate Air Cooler (Refurbishment) / 5 days / 24-Mar-09 / 28-Mar-09 / Saepudin
  24. Control and Monitoring (SCADA) (see detail at schedule below) / 15 days / 17-Jan-09 / 31-Jan-09 / Wawan
  25. Telecomunication / 15 days / 17-Jan-09 / 31-Jan-09 / Wawan
  26. Feed Heater A/B (visual check only) / 2 days / 1-Feb-09 / 2-Feb-09 / Saepudin
  27. CVC Separator + CVC Pump / 5 days / 3-Feb-09 / 7-Feb-09 / Yozi
  28. CVC Condensate Separator + CVC Condensate pump / 5 days / 8-Feb-09 / 12-Feb-09 / Yozi
  29. CVC Air Cooler / 5 days / 13-Feb-09 / 17-Feb-09 / Saepudin
  30. SOP for start-up / 30 days / 10-Feb-09 / 11-Mar-09 / Coord : Saepudin