System - duration - Start -Finished
- Manifold 62 days 28-Oct 15-Jan
- AWT system 156 days 11-Dec 21-May
- KO Drum 7 days 3-Feb 9-Feb
- Vent stack 4 days 10-Feb 13-Feb
- Utility Chemical Injection 8 days 12-Feb 19-Feb
- Cable tray 3 days 20-Feb 22-Feb
- Power source (Off/On-Plot) 7 days 27-Feb 5-Mar
- Major pipe racks 9 days 7-Mar 15-Mar
- AWT Pump A/B/C/D 33 days 7-Mar 8-Apr
- Condensate Separator 4 days 7-Mar 10-Mar
- AWT Separator 73 days 10-Mar 21-May
- Overflow Pumps 9 days 13-Mar 21-Mar
- Storm water pump 4 days 13-Mar 16-Mar
- Utility Fuel gas 16 days 14-Mar 29-Mar
- Priming Chambers 2.5 days 24-Mar 26-Mar
- Substation 8 days 29-Mar 5-Apr
- Surge vessel 22 days 30-Mar 20-Apr
- Lighting 3 days 5-Apr 7-Apr
- GLCC (Refurbishment) 16 days 8-Apr 23-Apr
- Air compressor package performance test 5.5 days 9-Apr 14-Apr
- Utility Steam 16 days 10-Apr 25-Apr
- Kill water 19 days 12-Apr 30-Apr
- Overflow Tanks (Refurbishment) 7 days 12-Apr 18-Apr
- Enclosed Flare (Refurbishment) 24 days 12-Apr 5-May
- Condensate Air Cooler (Refurbishment) 6 days 12-Apr 17-Apr
- CVC System 42 days 14-Apr 25-May
- Off Plot 7 days 14-Apr 20-Apr
- Condensate Transfer Pump 10 days 24-Apr 3-May
- Control and Monitoring 31 days 25-Apr 25-May
- Telecomunication 36 days 25-Apr 30-May
- Production Transfer Pump 13 days 26-Apr 8-May
- Feed Heater A/B 13 days 2-May 14-May
- On-Plot 23 days 3-May 25-May
- CVC Separator 21 days 4-May 24-May
- CVC Pump 19 days 7-May 25-May
- CVC Condensate pump 17 days 9-May 25-May
- CVC Condensate Separator 9 days 12-May 20-May
- CVC Air Cooler 8 days 16-May 23-May
- Infrastructure (Not required to finish during degassing milestone) 8 days 14-Jun 21-Jun