COMMISSIONING SUMMARY SCHEDULE

This schedule sorted by work sequencing

System - duration - Start -Finished
  1. Manifold 62 days 28-Oct 15-Jan
  2. AWT system 156 days 11-Dec 21-May
  3. KO Drum 7 days 3-Feb 9-Feb
  4. Vent stack 4 days 10-Feb 13-Feb
  5. Utility Chemical Injection 8 days 12-Feb 19-Feb
  6. Cable tray 3 days 20-Feb 22-Feb
  7. Power source (Off/On-Plot) 7 days 27-Feb 5-Mar
  8. Major pipe racks 9 days 7-Mar 15-Mar
  9. AWT Pump A/B/C/D 33 days 7-Mar 8-Apr
  10. Condensate Separator 4 days 7-Mar 10-Mar
  11. AWT Separator 73 days 10-Mar 21-May
  12. Overflow Pumps 9 days 13-Mar 21-Mar
  13. Storm water pump 4 days 13-Mar 16-Mar
  14. Utility Fuel gas 16 days 14-Mar 29-Mar
  15. Priming Chambers 2.5 days 24-Mar 26-Mar
  16. Substation 8 days 29-Mar 5-Apr
  17. Surge vessel 22 days 30-Mar 20-Apr
  18. Lighting 3 days 5-Apr 7-Apr
  19. GLCC (Refurbishment) 16 days 8-Apr 23-Apr
  20. Air compressor package performance test 5.5 days 9-Apr 14-Apr
  21. Utility Steam 16 days 10-Apr 25-Apr
  22. Kill water 19 days 12-Apr 30-Apr
  23. Overflow Tanks (Refurbishment) 7 days 12-Apr 18-Apr
  24. Enclosed Flare (Refurbishment) 24 days 12-Apr 5-May
  25. Condensate Air Cooler (Refurbishment) 6 days 12-Apr 17-Apr
  26. CVC System 42 days 14-Apr 25-May
  27. Off Plot 7 days 14-Apr 20-Apr
  28. Condensate Transfer Pump 10 days 24-Apr 3-May
  29. Control and Monitoring 31 days 25-Apr 25-May
  30. Telecomunication 36 days 25-Apr 30-May
  31. Production Transfer Pump 13 days 26-Apr 8-May
  32. Feed Heater A/B 13 days 2-May 14-May
  33. On-Plot 23 days 3-May 25-May
  34. CVC Separator 21 days 4-May 24-May
  35. CVC Pump 19 days 7-May 25-May
  36. CVC Condensate pump 17 days 9-May 25-May
  37. CVC Condensate Separator 9 days 12-May 20-May
  38. CVC Air Cooler 8 days 16-May 23-May
  39. Infrastructure (Not required to finish during degassing milestone) 8 days 14-Jun 21-Jun