CONSTRUCTION COMPLETE MEAN ....

  • FIRE AND SAFETY CONSTRUCTION READINESS
All fire fighting and safety equipments should be ready in construction phase before commissioned

  • MECHANICAL CONSTRUCTION READINESS
MIGAS certification and utility system should be completed in pre-commissioning construction punch list.
Pipe should be aligned at the pipe support and valve position & orientation has been aligned referring to Safety In Design (SID).
Leak test should be finished.
Tagging in equipment (mechanical, Electrical & Instrumentation) and piping at system should be conducted by construction team.

  • ELECTRICAL CONSTRUCTION READINESS
All panels and field instrumentation (that require the power) should be meger and continuity test.
Objective for each rotary equipment is Solorun. Solorun Test duration depend on CPI recommendation (not mandatory to 1 hour).
Lighting should be ready especially at building, shelter and lighting which have distribute light for some equipment such as pump, compressor, vessel, panel etc and field instrument that have related with measurement, setting and safety/shutdown system.

  • INSTRUMENT CONSTRUCTION READINESS
Field instrumentasi had been installed and calibrated/certified.
For all instrumentation that have related with measurment and setting point should be QC passed calibration and/or third party.
Instrument cable should be meger & continuity from : field instrument - Control room - MCC.

  • CIVIL CONSTRUCTION READINESS
Radiness of Civil construction are support pipe/pipe rack/cable rack installed, dress-up, acess road and platform referring to SID include grouting for all pump and compressor, shelter have to be finished, plumbing system, and drainage/OWS around that system to OWS collection