- FIRE AND SAFETY CONSTRUCTION READINESS
- MECHANICAL CONSTRUCTION READINESS
Pipe should be aligned at the pipe support and valve position & orientation has been aligned referring to Safety In Design (SID).
Leak test should be finished.
Tagging in equipment (mechanical, Electrical & Instrumentation) and piping at system should be conducted by construction team.
- ELECTRICAL CONSTRUCTION READINESS
Objective for each rotary equipment is Solorun. Solorun Test duration depend on CPI recommendation (not mandatory to 1 hour).
Lighting should be ready especially at building, shelter and lighting which have distribute light for some equipment such as pump, compressor, vessel, panel etc and field instrument that have related with measurement, setting and safety/shutdown system.
- INSTRUMENT CONSTRUCTION READINESS
For all instrumentation that have related with measurment and setting point should be QC passed calibration and/or third party.
Instrument cable should be meger & continuity from : field instrument - Control room - MCC.
- CIVIL CONSTRUCTION READINESS